March 2024: A Closer Look at Construction Progress

March 19, 2024
5
min read
Significant development progress has occurred at June Lake over the past couple of months. Here are the latest updates:

Infrastructure

The I-65 and June Lake Boulevard Interchange is rapidly advancing and is expected to open this May.

The water tank project is nearing completion, and construction along Marston Avenue is proceeding as scheduled.

Watertank progress.
Marston Ave. Progress

 

Residences

Vertical construction on the first multi-family apartments, Solstice at June Lake, began last month and has seen substantial progress. Framing is well underway, with Phase 2 soon to follow. Leasing is scheduled to commence in June, with the first move-ins anticipated by late June.  

Progress on the initial phase of homes at Saddlewalk is continuing steadily. Families are preparing to move into their new homes as early as April (next month!).  

Additionally, the first four homes at Preserve are making significant strides, with windows and brickwork nearing completion.

A plant icon

Recent Updates

Recent update featured image
5
min read

October 2024: A Fresh Look at Development Progress

June Lake continues to transform into a vibrant, mixed-use community, with significant progress made across its residential and commercial
Recent update featured image
1
min read

Turning of the Valve: Spring Hill Water Tank

The City of Spring Hill held a Turning of the Valve ceremony to celebrate the completion of the new 3-million-gallon water tank
Recent update featured image
4
min read

New Interchange at June Lake Blvd & I-65 Opens!

The long-awaited June Lake Boulevard/I-65 interchange, exit 55, opens today, providing a direct gateway to Spring Hill and seamless access t